Sec. 1. The rules adopted under IC 13-23-1-2(c)(6) may allow evidence of financial responsibility in one (1) or a combination of the following forms: (1) Insurance. (2) Guarantee. (3) Surety bond. (4) Letter of credit. (5) Qualification as a self-insurer. (6) Any other method satisfactory to the commissioner and the Administrator of the United States […]
Sec. 2. The rules adopted under IC 13-23-1-2(c)(6) may require the use of certain policy provisions or contract terms, including provisions or terms concerning the following: (1) The minimum amount of coverage required for various classes and categories of underground storage tanks established under section 4 of this chapter. (2) Conditions or defenses that are […]
Sec. 3. (a) The commissioner may provide a method under which the owner or operator of an underground storage tank may establish evidence of financial responsibility as required under sections 1 and 2 of this chapter and 42 U.S.C. 6991b(c)(6) with respect to the part of the potential liability of the owner or operator that […]
Sec. 4. (a) The rules adopted under IC 13-23-1-2(c)(6) may require a minimum amount of coverage for particular classes or categories of underground storage tanks containing petroleum. Minimum coverage amounts established under this subsection must be at least one million dollars ($1,000,000) for each occurrence, with an appropriate aggregate amount. (b) The board may by […]
Sec. 5. (a) The commissioner, upon the application of any affected person or in the absence of any application, may suspend enforcement of the financial responsibility requirements for a particular class or category of underground storage tanks if the commissioner determines that the following conditions exist: (1) The methods of financial responsibility satisfying the requirements […]
Sec. 6. (a) If: (1) the owner or operator of an underground storage tank is in bankruptcy, reorganization, or arrangement under the federal bankruptcy law; or (2) despite the exercise of reasonable diligence, no state or federal court could obtain jurisdiction over an owner or operator likely to be solvent at the time of judgment; […]
Sec. 7. The provisions of IC 13-11-2-241(d)(10) and sections 1(6) and 5(c) of this chapter requiring the concurrence of the Administrator of the United States Environmental Protection Agency for an action of the board or commissioner to be effective are nullified if the Administrator grants to the commissioner, under the program approved under Section 9004 […]