573.1 Definitions. For the purpose of this chapter: 1. “Construction”, in addition to its ordinary meaning, includes repair, alteration and demolition. 2. “Material” shall, in addition to its ordinary meaning, embrace feed, gasoline, kerosene, lubricating oils and greases, provisions and fuel, and the use of forms, accessories, and equipment, but shall not include personal expenses […]
573.10 Time of filing claims. Claims may be filed with said officer as follows: 1. At any time before the expiration of thirty days immediately following the completion and final acceptance of the improvement. 2. At any time after said thirty-day period, if the public corporation has not paid the full contract price as herein […]
573.11 Claims filed after action brought. The court may permit claims to be filed with it during the pendency of the action hereinafter authorized, if it be made to appear that such belated filing will not materially delay the action. [C24, 27, 31, 35, 39, §10309; C46, 50, 54, 58, 62, 66, 71, 73, 75, […]
573.12 Payments and retention from payments on contracts. 1. Retention. a. Payments made under contracts for the construction of public improvements, unless provided otherwise by law, shall be made on the basis of monthly estimates of labor performed and material delivered, as determined by the project architect or engineer. The public corporation shall retain from […]
573.13 Inviolability and disposition of fund. A public corporation shall not be permitted to plead noncompliance with section 573.12 and the retained percentage of the contract price, which in no case shall be more than five percent, constitutes a fund for the payment of claims for materials furnished and labor performed on the improvement and […]
573.14 Retention of unpaid funds. 1. The fund provided for in section 573.13 shall be retained by the public corporation for a period of thirty days after the completion and final acceptance of the improvement. If at the end of the thirty-day period claims are on file, the public corporation shall continue to retain from […]
573.15 Claim against retainage or bond. 1. A person, firm, or corporation that has performed labor for or furnished materials, service, or transportation to a subcontractor shall not be entitled to a claim against the retainage or bond under this chapter unless the person, firm, or corporation that performed the labor or furnished the materials, […]
573.15A Early release of retained funds. Notwithstanding section 573.14, a public corporation may release retained funds upon completion of ninety-five percent of the contract in accordance with the following: 1. Any person, firm, or corporation who has, under contract with the principal contractor or with subcontractors, performed labor, or furnished materials, service, or transportation, in […]
573.16 Optional and mandatory actions — bond to release. 1. The public corporation, the principal contractor, any claimant for labor or material who has filed a claim, or the surety on any bond given for the performance of the contract, may, at any time after the expiration of thirty days, and not later than sixty […]
573.17 Parties. The official board or officer letting the contract, the principal contractor, all claimants for labor and material who have filed their claim, and the surety on any bond given for the performance of the contract shall be joined as plaintiffs or defendants. [C24, 27, 31, 35, 39, §10314; C46, 50, 54, 58, 62, […]
573.18 Adjudication — payment of claims. 1. The court shall adjudicate all claims for which an action is filed under section 573.16. Payments from the retained percentage, if still in the hands of the public corporation, shall be made in the following order: a. Costs of the action. b. Claims for labor. c. Claims for […]
573.19 Insufficiency of funds. When the retained percentage is insufficient to pay all claims for labor or materials, the court shall, in making distribution under section 573.18, order the claims in each class paid in the order of filing the same. [C97, §3102; S13, §1989-a57; C24, 27, 31, 35, 39, §10316; C46, 50, 54, 58, […]
573.2 Public improvements — bond — waiver and remedies. 1. Contracts for the construction of a public improvement shall, when the contract price equals or exceeds twenty-five thousand dollars, be accompanied by a bond, with surety, conditioned for the faithful performance of the contract, and for the fulfillment of other requirements as provided by law. […]
573.20 Converting property into money. When it appears that the unpaid portion of the contract price for the public improvement, or a part thereof, is represented in whole or in part, by property other than money, or if a deposit has been made in lieu of a surety, the court shall have jurisdiction thereover, and […]
573.21 Attorney fees. The court may tax, as costs, a reasonable attorney fee in favor of any claimant for labor or materials who has, in whole or in part, established a claim. [C97, §3103; S13, §1989-a58; C24, 27, 31, 35, 39, §10318; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, §573.21]
573.22 Unpaid claimants — judgment on bond. If, after the said retained percentage has been applied to the payment of duly filed and established claims, there remain any claims that are unpaid in whole or in part, judgment shall be entered for the amount of the claims that are unpaid against the principal and sureties […]
573.23 Abandonment of public work — effect. When a contractor abandons the work on a public improvement or is legally excluded from work on a public improvement, the improvement shall be deemed completed for the purpose of filing claims as provided in this chapter, from the date of the official cancellation of the contract. The […]
573.24 Notice of claims to state department of transportation. If payment for such improvement is to be made in whole or in part from the primary road fund, the county auditor shall immediately notify the state department of transportation of the filing of all claims. [C24, 27, 31, 35, 39, §10321; C46, 50, 54, 58, […]
573.25 Filing of claim — effect. The filing of any claim shall not work the withholding of any funds from the contractor except the retained percentage, as provided in this chapter. [C24, 27, 31, 35, 39, §10322; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, §573.25]
573.26 Public corporation — action on bond. Nothing in this chapter shall be construed as limiting in any manner the right of the public corporation to pursue any remedy on the bond given for the performance of the contract. [C24, 27, 31, 35, 39, §10323; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, […]