Except as otherwise provided in NRS 338.555, 338.560 and 338.565: 1. Each contractor shall disburse money paid to the contractor pursuant to this chapter, including any interest which the contractor receives, to his or her subcontractors and suppliers within 10 days after the contractor receives the money, in direct proportion to the subcontractors’ and suppliers’ […]
1. If a public body and a contractor enter into a contract for a public work, the contractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract. 2. After […]
1. Except as otherwise provided in subsection 2 of NRS 338.555, a contractor may withhold from a progress payment or retainage payment an amount sufficient to pay: (a) The expenses the contractor reasonably expects to incur as a result of the failure of his or her subcontractor or supplier to comply with the subcontract or […]
1. If a contractor makes payment to a subcontractor or supplier more than 10 days after the occurrence of any of the following acts or omissions: (a) The contractor fails to pay his or her subcontractor or supplier in accordance with the provisions of subsection 1 of NRS 338.550; (b) The contractor fails to give […]
Within 5 working days after a contractor receives a written request from a subcontractor or supplier of his or her subcontractor or supplier with respect to a subcontract which has not been fully performed, the contractor shall notify the subcontractor or supplier of his or her subcontractor or supplier in writing of the following: 1. […]