Section 702 – Parties — Consolidation of separate actions.

38-1a-702. Parties — Consolidation of separate actions. (1) In an action under this part, subject to the time restrictions under Subsection 38-1a-701(2): (a) a claimant who is not contesting the claim of another claimant may join as a plaintiff; (b) a claimant who fails or refuses to become a plaintiff may be made a defendant; […]

Section 703 – Order of satisfaction if multiple liens on same property.

38-1a-703. Order of satisfaction if multiple liens on same property. If liens are claimed against the same property the decree shall provide for their satisfaction in the following order: (1) subcontractors who are laborers or mechanics working by the day or piece, but who have not furnished materials; (2) all other subcontractors and all materialmen; […]

Section 704 – Sale of property — Redemption — Disposition of proceeds.

38-1a-704. Sale of property — Redemption — Disposition of proceeds. (1) The court shall cause the property to be sold in satisfaction of the liens and costs as in the case of a foreclosure of a mortgage, subject to the same right of redemption. (2) If the proceeds of sale after the payment of costs […]

Section 705 – Deficiency judgment.

38-1a-705. Deficiency judgment. A claimant whose preconstruction or construction lien is not paid in full through an enforcement action as provided in this part may: (1) have judgment for the unpaid balance entered against the person liable; and (2) execute on the judgment in the same manner as execution on judgments generally. Enacted by Chapter […]

Section 706 – Apportionment of costs — Costs and attorney fees to subcontractor.

38-1a-706. Apportionment of costs — Costs and attorney fees to subcontractor. (1) Except as provided in Section 38-11-107, the court shall apportion costs between the owner and original contractor according to the right of the case. (2) The court shall award a subcontractor with a valid preconstruction or construction lien: (a) all of the subcontractor’s […]

Section 707 – Attorney fees — Offer of judgment.

38-1a-707. Attorney fees — Offer of judgment. (1) Except as provided in Section 38-11-107 and in Subsection (2), in any action brought to enforce any lien under this chapter the successful party shall be entitled to recover reasonable attorney fees, to be fixed by the court, which shall be taxed as costs in the action. […]