Section 202 – Public utility to provide standard cost and estimated excess cost.

54-14-202. Public utility to provide standard cost and estimated excess cost. (1) (a) A public utility shall provide the information described in Subsection (1)(b) if a local government: (i) is considering imposing requirements or conditions on construction of a facility that may result in an estimated excess cost and requests that the public utility provide […]

Section 203 – Actual excess cost.

54-14-203. Actual excess cost. (1) If a local government issues a permit, authorization, approval, exception, or waiver based upon its agreement to pay for the actual excess cost of a facility, the local government shall within 30 days either accept the estimate of excess cost as the actual excess cost of a facility or request […]

Section 204 – Requirements or conditions on facility considered waived if local government does not pay for actual excess cost 30 days before construction.

54-14-204. Requirements or conditions on facility considered waived if local government does not pay for actual excess cost 30 days before construction. Any requirement or condition in any permit, authorization, approval, exception, or waiver of a local government for a facility that imposes an actual excess cost shall be considered waived if the local government […]