US Lawyer Database

For Lawyer-Seekers

YOU DESERVE THE BEST LAWYER

Home » US Law » 2022 Utah Code » Title 54 - Public Utilities » Chapter 17 - Energy Resource Procurement Act » Part 3 - Resource Plans and Significant Energy Resource Approval

Section 301 – Review of integrated resource plan action plans.

54-17-301. Review of integrated resource plan action plans. (1) An affected electrical utility shall file with the commission any action plan developed as part of the affected electrical utility’s integrated resource plan to enable the commission to review and provide guidance to the affected electrical utility. (2) (a) In accordance with Title 63G, Chapter 3, […]

Section 302 – Approval of a significant energy resource decision required.

54-17-302. Approval of a significant energy resource decision required. (1) If pursuant to Part 2, Solicitation Process, an affected electrical utility is required to conduct a solicitation for a significant energy resource or obtains a waiver of the requirement to conduct a solicitation under Section 54-17-501, but does not obtain a waiver of the requirement […]

Section 303 – Cost recovery.

54-17-303. Cost recovery. (1) (a) Except as otherwise provided in this section, if the commission approves a significant energy resource decision under Section 54-17-302, the commission shall, in a general rate case or other appropriate commission proceeding, include in the affected electrical utility’s retail electric rates the state’s share of costs: (i) relevant to the […]

Section 304 – Order to proceed.

54-17-304. Order to proceed. (1) (a) In the event of a change in circumstances or projected costs, an affected electrical utility may seek a commission review and determination of whether the affected electrical utility should proceed with the implementation of an approved significant energy resource decision. (b) In making a determination under this Subsection (1), […]