Section 103 – Electric vehicle incentive program.

Effective 5/10/2016 54-20-103. Electric vehicle incentive program. (1) The commission shall, before July 1, 2017, authorize a large-scale electric utility to establish a program that promotes customer choice in electric vehicle charging equipment and service that includes: (a) an incentive to a large-scale electric utility customer to install or provide electric vehicle infrastructure; (b) time […]

Section 104 – Clean coal technology program.

Effective 5/10/2016 54-20-104. Clean coal technology program. (1) Subject to Subsection (2), the commission shall authorize, before July 1, 2017, and, subject to funding, approve a program that authorizes a large-scale electric utility to investigate, analyze, and research clean coal technology. (2) The commission may review the expenditures made by a large-scale electric utility for […]

Section 105 – Innovative utility programs.

Effective 5/14/2019 54-20-105. Innovative utility programs. (1) The commission may authorize, subject to funding available under Subsection 54-7-12.8(6)(b)(ii)(B), a large-scale electric utility to implement programs that the commission determines are in the interest of large-scale electric utility customers to provide for the investigation, analysis, and implementation of: (a) an economic development incentive rate; (b) a […]

Section 106 – Extension of pilot program.

Effective 5/10/2016 54-20-106. Extension of pilot program. Before the first day of the legislative session in the final year of the pilot program period, the commission shall submit a report and recommendation to the Legislature regarding whether, in the discretion of the commission, the Legislature should, for the sustainable transportation and energy plan: (1) extend […]

Section 107 – Other programs.

Effective 5/14/2019 54-20-107. Other programs. The commission may authorize a large-scale electric utility or a large-scale natural gas utility to establish a program in addition to the programs described in this chapter if the commission determines that the program is cost-effective and in the public interest. Amended by Chapter 460, 2019 General Session